Current delivery times from our manufacturers
For lead time or stock information of specific parts, please use the seach to find the part in our webshop or contact us. The current general overview can be found in the following table.
Amphenol
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 16 - 22 Weeks | no |
Antenova
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Antennas (SMD, Embedded, External, Active GNSS) Allocation: no | 9 - 10 weeks | no |
Capxon
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Electrolyte wired Allocation: no | 20 - 28 weeks | no |
CKINGWAY
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
TFT Displays Allocation: no | 12-24 weeks | no |
CML
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
SOP und TSSOP ICs Allocation: no | 10 - 12 weeks | no | |
CMX869B Allocation: | 20 or more weeks | ||
CMX7031 / CMX7032 / CD636 Allocation: | 20 or more weeks | ||
SCT3258 / 3268 Allocation: | 24 weeks | ||
QFN ICs Allocation: no | 14 - 16 weeks | no | |
CMX86x modem family Allocation: no | 20 or more weeks | no | |
CMX994E / CMX994G / RP571 / SCT3811 Allocation: | 33 weeks | ||
CMX148 / CD686 / CMX885 Allocation: | 20 weeks | ||
CMX901QT8 Allocation: no | 20 or more weeks | no | |
CMX7041/2 AIS device family Allocation: no | 20 or more weeks | no |
CONEC
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 8-16 weeks | no |
Congatec
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
COM's
with reference to INTEL, AMD
Allocation: yes
|
with reference to INTEL, AMD | 30 - 43 weeks | yes |
Cooling
HSP and CSAP
Allocation: no
|
HSP and CSAP | 10 - 19 weeks | no |
COM's
with reference to NXP
Allocation: yes
|
with reference to NXP | 42-52 weeks | yes |
Baseboard
increased component lead time
Allocation: no
|
increased component lead time | 24 - 42 weeks | no |
DARFON
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
MLCC und MLCI Allocation: no | 14 - 16 weeks | no |
DEGSON
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 10 - 12 weeks | no |
ept
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 8 - 16 weeks | no |
ETD
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
TFT Displays, Grafik Displays, Character Displays Allocation: no | 12 - 24 weeks | no |
finder
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: partly | 14 - 35 weeks | partly |
Harting
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 8 - 16 weeks | no |
Honeywell
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 20 - 28 weeks | no |
Hosonic
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
MHz oscillators Allocation: no | 8 - 12 weeks | no | |
Quartz resonators
leadtime and availability depends on package size
Allocation: no
|
leadtime and availability depends on package size | 6 - 10 weeks | no |
Ilme
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 8 - 16 weeks | no |
Innodisk
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Flash CF Card Allocation: no | 2 - 6 weeks | no | |
Flash SLC Allocation: no | 2 - 6 weeks | no | |
Flash MLC Allocation: yes | 2 - 6 weeks | yes | |
DRAM Allocation: no | 2 - 4 weeks | no | |
DRAM DDR3 und DDR4
IC organisation 512Mx8 and 256Mx16 Alternative 1Gx8 at standard delivery time
Allocation: yes
|
IC organisation 512Mx8 and 256Mx16 Alternative 1Gx8 at standard delivery time | 8 - 14 weeks | yes |
Flash TLC Allocation: no | 2-6 weeks | no |
JYA NAY
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Ceramics Allocation: no | 16 - 20 weeks | no |
KDS
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Quartz resonators
some goods available from stock
Allocation: no
|
some goods available from stock | 10 - 14 weeks | no |
Oscillators and TCXOs Allocation: no | on request | no |
KEMET
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Tantal MnO2
leadtime and availability heavily depends on package size
Allocation: no
|
leadtime and availability heavily depends on package size | 10 - 50 weeks | no |
Supercaps Allocation: no | 22 - 30 weeks | no | |
Tantal Polymer Allocation: no | 20 - 50 weeks | no | |
Electrolyte Allocation: no | 24 - 38 weeks | no | |
Filter Allocation: no | 40 - 50 weeks | no | |
Film Allocation: no | 28 - 36 weeks | no | |
Sensors Allocation: no | 22 - 40 weeks | no | |
Inductors Allocation: no | 30 - 40 weeks | no | |
Magnetics Allocation: no | 28 - 36 weeks | no | |
MLCC / Ceramics
leadtime and availability depends on series/size of product
Allocation: no
|
leadtime and availability depends on series/size of product | 10 - 50 weeks | no |
Flex Suppressor (EMI Sheet) Allocation: no | 10 - 12 weeks | no |
KJ
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Electrolyte SMD Allocation: no | 26-42 weeks | no |
MicroCrystal
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
RTC modules
some goods available from stock
Allocation: no
|
some goods available from stock | 8 - 10 weeks | no |
kHz quartz resonators Allocation: no | 7-10 weeks | no |
ORTUSTECH
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
TFT Displays Allocation: no | 22-28 weeks | no |
Provertha
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 8-16 weeks | no |
Schaffner
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
3 Phase filter Allocation: no | 22-24 weeks | no | |
1 Phase filter Allocation: no | 22-24 weeks | no | |
Chokes Allocation: no | 22-24 weeks | no | |
Sinusoidal filters and mains chokes Allocation: no | 24-26 weeks | no | |
Special types (FS & RU) Allocation: no | 28-30 weeks | no |
Schaltbau
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Allocation: no | 10-12 weeks | no |
SiTime
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
New order (depending on series)
Replenishment Lead time for Standard Series, SiT1602, SiT8008, SiT8009,SiT9120, SiT9121, SiT9122
Allocation: no
|
Replenishment Lead time for Standard Series, SiT1602, SiT8008, SiT8009,SiT9120, SiT9121, SiT9122 | 12 - 14 weeks | no |
Programmed by SE
Standard Types: SiT8008/9, SiT9121/2, SiT8918/9, SiT1602, SiT9120
Allocation: no
|
Standard Types: SiT8008/9, SiT9121/2, SiT8918/9, SiT1602, SiT9120 | 2-4 weeks | no |
Taoglas
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Antennas Allocation: no | 12-14 weeks | no |
THINGWELL
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Displays (Grafik, Character, ePaper) Allocation: no | 12 - 28 weeks | no |
u-blox
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Evalkits
pls contact sales to check individual lead time
Allocation: no
|
pls contact sales to check individual lead time | 16 weeks | no |
GNSS Modules
ZOE M8 modules up to 30 weeks
Allocation: no
|
ZOE M8 modules up to 30 weeks | 8-30 weeks | no |
Cellular Modules Allocation: no | 8-12 weeks | no | |
Short Range Modules Allocation: no | 8-16 weeks | no |
Wima
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Foil Allocation: no | 14-18 weeks | no |
Winstar
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Displays (TFT and Smart) Allocation: no | 12 - 24 weeks | no | |
Displays (Grafik and Character) Allocation: no | 14-18 weeks | no | |
OLED modules Allocation: no | 14-18 weeks | no |
Xsens
Area | actual delivery time (approx.) | Allocation | |
---|---|---|---|
Modules (SMD, Rugged) and Rugged devices
Small Qty available in approx 2-3 weeks
Allocation: no
|
Small Qty available in approx 2-3 weeks | 9-10 weeks | no |
250 Reels SMD modules Allocation: no | 9 - 10 weeks | no |